S.R. 4013 Section A10

Michael Kilgore

Cost: $3.29 million
Project Length:1,182 Feet
Client: PennDOT Engineering District 12-0
Contact: Mr. Barry Lyons (724 439-7336)

Bridge Replacement - The project included a three span (182’ - 2 ¾” c/c brgs.) precast concrete
spread box beam bridge over Norfolk Southern’s dual track high-speed railroad. The project included
approximately 1,000 feet of roadway relocation and reconstruction to accommodate required vertical
clearances over the railroad as well as to maintain traffic throughout construction.
 

 

S.R. 0381 Section C10

Michael Kilgore


 Cost: $2.7 Million
Client: PennDOT Engineering District 12-0

Meadow Run Bridge Replacement and Roadway Improvements - This project included a Three-Span Continuous Composite Prestressed Concrete Bridge. It also included 1,000 feet of roadway approach and a connection to existing S.R. 2019. The structure was constructed in half-widths so as to maintain traffic at all times.

 

S.R. 4025 Section A00

Michael Kilgore

Cost: $3.0 Mil.
Project Length:873 feet, 0.165 mile
Client: PennDOT Engineering District 12-0
Contact: Mr. Jerry Bendo (Retired)

Bridge Replacement - This project included a Three-Span (Overall span length 296’) Continuous Composite
Prestressed Concrete Bridge which carries S.R. 4025 over S.R. 4027, Reed Street, and Coal Run. The entire
length of the project was 873 feet, 0.165 mile. The structure was replaced on a new alignment to improve geometry
and allow traffic to be maintained at all times.