S.R. 4004, Section L02
Michael Kilgore
Project Cost: $0.917 million
Client: Engineering District 11-0
Contact: Mr. Robert W. Turoczy, P.E. (412-429-4899)
Project Letting - January 2017
Beaver County- The project consists of the replacement of an existing concrete deck on a two-span prestressed concrete adjacent box beam bridge (201.5’ overall span). The project also includes the necessary analysis and detailing to eliminate the existing deck joint over the pier, producing a continuous superstructure. Minor approach roadway and substructure repair work will also be part of the construction contract.