S.R. 0040 Section 129
Michael Kilgore
Project Cost: $1.70 million
Client: Engineering District 12-0
Project Manager - Mr. William Beaumariage (724-439-7378)
Roadway Realignment and Safety Improvements - Chalk Hill, Fayette County - The project consisted of re-aligning the intersection of S.R. 0040 and S.R. 2010 to 1,200-feet west of the previous intersection to provide adequate sight distance. The realignment of S.R. 2010 required a new traffic signal, addition of a designated left-turn lane and the widening and resurfacing of the S.R. 0040 mainline.