Filtering by Tag: Centre

S.R. 0080 Section B09

Michael Kilgore

Project Cost: $43.0 million
Project Length: 7.22 Miles WB 7.29 Miles EB
Client: PennDOT Engineering District 2-0
Contact: Mr. Mark Kucherer, P.E. (814-765-0440)

Interstate Roadway and Bridge Reconstruction - This project includes a Dual Five-Span (Overall span length - 439.5 feet WB/458.0 feet EB) carrying S.R. 0080 WB and EB over S.R. 0220 (Milesburg Interchange); a Dual Three-Span (Overall span length - 274.0 feet WB and EB) carrying S.R. 0080 WB and EB over Bald Eagle Creek; and a Dual Single-Span (Overall span length - 65.2 feet WB/73.0 feet EB) carrying S.R. 0080 WB and EB over S.R. 1006. The project also includes the reconstruction of the Milesburg Interchange (S.R. 0080/S.R. 0220).  

S.R. 4002 Section A02/A03

Michael Kilgore

Cost: $1.275 million
Client: Engineering District 2-0
Contact: Mr. Craig Sattesahn, P.E. (814-765-0678)
Project Letting - 2011

Structure Replacements - This project included the replacement of two (2) existing bridges with a prestressed concrete spread box beam bridge (69’ span - Section A02) with integral abutments, and a precast concrete box culvert (24’ span - Section A03). The projects also included 400’ and 515’ of roadway reconstruction for Sections A02 and A03 respectively. 
 

S.R. 3017 Section A01

Michael Kilgore

Project Cost: $1.44 million
Project Length: 504'
Project Letting - 2011
Client: PennDOT Engineering District 2-0
Contact: Mr. Mark Kucherer, P.E. (814-765-0440)

Bald Eagle Creek - This project included the replacement of an existing bridge with a prestressed concrete spread box beam bridge (79’ span). The project also included 425’ of approach roadway reconstruction.