S.R. 0038 Section 259

Michael Kilgore

Before

Before

After

After

IMG_3535.JPG

Project Cost: $862,651
Client: PennDOT District 10-0
Contact: Doug Zubal, P.E.
Project Letting: December 2017

S.R. 0038, Section 259 is located in Concord Township, Butler County.  The project consists of the replacement of the reinforced concrete arch culvert that carries SR 0038 over a tributary to Connoquenessing Creek with a precast reinforced concrete box culvert.  The horizontal and vertical alignment match the existing roadway. Minimal roadway approach work was included for approximately 200 feet on the western approach and 250 feet on the eastern approach. One lane of traffic was maintained throughout construction of the project via half-width construction, controlled with temporary traffic signals.   

 

S.R. 2002 Section 250

Michael Kilgore

After

After

After

After

After

After

Cost: - $1.663 Million
Client: PennDOT District 10-0
Contact: Ms. Melanie Percha, P.E. (724-357-4804)
Project Letting: October 2015.

(Herman Road Bridge) - Butler County - This project included the phased replacement of a deteriorated two-span non-composite adjacent box beam bridge over Coal Run with a single span shallow fabricated structural steel bridge (73.5’ c-c brgs.). The project also included 505’ of approach roadway construction and pedestrian facilities.

S.R. 0356 Section 251

Michael Kilgore

Cost: $1.1 million
Project Length: 284'
Client: PennDOT Engineering District 10-0


SR 0356, Section 251 – Butler County – Rehabilitation of a four span (284’ total span) combination adjacent/spread box beam bridge carrying SR 0356 over SR 0028. The rehabilitation work included the replacement of the existing concrete deck and repairs to the existing beams and substructures. The bridge rehabilitation was incorporated into a 3R project prepared by District 10-0.